Use this planner to clarify what a supplier’s minimum order quantity actually applies to and to build a schedule around approvals, material procurement, production, inspection and dispatch. It complements a sourcing guide by providing fields to record supplier commitments and buyer dependencies for each purchase order.

Part A — Order and product details

Buyer / project: ____________________   Supplier: ____________________

Product / SKU family: ____________________   Target delivery date: ____________________

Destination / trade term: ____________________   Purchase order reference: ____________________

Part B — MOQ breakdown

Ask the supplier to identify the level at which each MOQ applies. The product MOQ may not be the same as the fabric, dyeing, printing, filling, backing or packaging minimum.

MOQ driverSupplier minimumBuyer requirementShortfall / extra quantityCommercial impact
Per style / design________________________________
Per colour / print________________________________
Per size / dimension________________________________
Fabric / yarn / material batch________________________________
Printing / dyeing / finishing________________________________
Labels / packaging / cartons________________________________

Part C — Quantity options

OptionOrder quantityUnit priceMOQ / setup chargeTotal order valueComments
Trial order________________________________________
Commercial order________________________________________
Repeat / scale order________________________________________

Part D — Production milestone planner

Record the agreed planned date, actual date, owner, dependency and evidence for each milestone. Confirm whether the supplier’s quoted lead time starts after purchase order, deposit, final sample approval, artwork approval or material readiness.

MilestonePlanned dateActual dateOwnerDependency / evidenceStatus
RFQ and specification confirmed__________________Approved brief______
Supplier / factory approved__________________Assessment record______
Proto / lab dip / strike-off__________________Sample submitted______
Final sample approval__________________Written approval______
Testing / label / packaging approval__________________Reports and artwork______
PO and deposit completed__________________PO / payment record______
Bulk materials ready__________________Material status______
Bulk production start__________________Production plan______
In-line / DUPRO review__________________Inspection report______
Final inspection and corrective action__________________Inspection / closure______
Packing and shipment documents__________________Packing list / invoices______
Dispatch / cargo handover__________________Handover confirmation______

Part E — Delay and escalation log

Issue / riskImpact on critical pathContainment / recovery actionOwnerNext review date
________________________________________________________________
________________________________________________________________

Planning rules

  • Separate sample-development time from bulk-production time.
  • Record lead-time start and end points in writing.
  • Include buyer approval time and material procurement in the critical path.
  • Show subcontracted processes and their delivery dependencies.
  • Plan inspection, corrective action, packing and dispatch as distinct milestones.
  • Use a recovery plan when a critical milestone slips; do not silently compress quality checks.

Related resources: MOQ and Lead Times for Indian Manufacturers, MOQs, Sampling and Production Planning and India Sourcing RFQ Template.